8.3 Administrative Closure

The EU Project Manager (EUPM) ensures that all project deliverables have been accepted by the Contracting Authority (CA) and, with the help of the Project Support Team (PST), that all project documentation and records are up to date, reviewed, organised and project expenses have been paid, recorded, and archived. The Project Core Team (PCT) is now officially dissolved, and all resources are released.

The project is officially closed once all Closing Phase activities are completed and the Contracting Authority (CA) has approved the project.

Key participants Description
EU Project Manager (EUPM) Oversees all closure activities and the release of project resources
Partners Project Managers (PtEUPM) Support the EU Project Manager (EUPM) in all closure activities related to their assigned part of project activities
Financial Manager (FM) / Partner Financial Managers (PtFM) Support the EU Project Manager (EUPM) in in all closure activities related to the financial part of the project
Project Support Office (PSO) Assists in reviewing, organising and archiving all project
documentation
Contracting Authority (CA) Has final approved of the project.

Inputs

Steps

ARSCI

Closing CA PSC GO DC PTG CR EUPM PtEUPM PCT PST (FM)
Administrative Closure A R I I I I I I I S

8.2 Project Final Report

Post-closing obligations