Following the Project-End Review Meeting, the overall narrative and financial part of the project is detailed in the Project Final Report that documents the activities implemented, the deliverable produced, the expenses incurred as well as the objectives and impacts achieved.
The structure and content of the Final Project Report is defined by the Contracting Authority (CA) in the Grant Agreement and is generally aligned with the Progress and Interim Report. The Project Final Report should be used as a knowledge base for future projects.
Key participants | Description |
---|---|
EU Project Manager (EUPM) | Responsible for the elaboration and submission of the Final Project Report |
Partners Project Managers (PtEUPM) | Support the EU Project Manager (EUPM) in the elaboration and submission of the Final Project Report for the assigned part of project activities |
Financial Manager (FM) / Partner Financial Managers (PtFM) | Support the EU Project Manager (EUPM) in the elaboration of the financial section of the Project Final Report |
Project Steering Committee (PSC) | Accountable for the submission of the Final Project Report. |
Closing | CA | PSC | GO | DC | PTG | CR | EUPM | PtEUPM | PCT | PST |
---|---|---|---|---|---|---|---|---|---|---|
Final Project Report | I | A | C | S | C | C | R | S | C | S |